City of Spring Hill
Ask for written confirmation of sewer availability, vested rights, capacity allocation, flow-meter requirements, development status, and any current amendment that applies.
What the current capacity framework says, what it does not say, and how to check a parcel before you buy, design, or build.
It's still in effect as of September 2026. Since August 2025 a TDEC consent order has blocked new sewer connections for Spring Hill projects without vested rights. Ordinance 25-29, adopted January 5, 2026, split the plant's remaining capacity among existing agreements, ready lots, and a small reserve. Septic is possible on some lots, but only with its own TDEC or Williamson County permit.
A sewer moratorium is a freeze on new connections to a public sewer system, usually because the treatment plant can't take more flow without breaking its discharge permit. Homes already hooked up keep flushing as normal. What stops is new development that would add wastewater. Spring Hill's came from the state after the city self-reported 29 effluent violations at its plant between 2023 and 2025.
The August 2025 consent order restricted sewer connections for projects without vested rights. Spring Hill later paused portions of development processing while it measured remaining plant capacity. On January 5, 2026, the board adopted Ordinance 25-29 and replaced that broad pause with a one-time capacity-allocation framework.
The allocation numbers show how tight the math is. Ordinance 25-29 calls itself a one-time allocation of all remaining treatment capacity: 207,403 gallons per day for existing development agreements, 62,500 gallons per day for 250 permit-ready vacant lots, 65,000 for critical infrastructure, and a 100,000-gallon discretionary reserve that Ordinance 26-01 later amended. Allocated projects must install flow meters. The ordinance states plainly that no additional development capacity remains available.
So the January vote reopened processing only for applications that fit the framework. It didn't announce new sewer capacity. Read the city's framework summary and the current ordinance index.
Spring Hill self-reported 29 wastewater-treatment-plant effluent exceedance violations, according to the city's official summary.
The Board of Mayor and Aldermen accepted TDEC Consent Order WPC2025-0093. The order restricted new sewer connections for projects without vested sewer rights.
The city temporarily suspended and then extended parts of development processing while staff evaluated remaining wastewater capacity and an allocation method.
The board adopted Ordinance 25-29 on second reading. It established a one-time sewer-capacity allocation framework and lifted prior development suspensions only as allowed by that framework.
Ordinance 26-01, amending Section 2(F) of Ordinance 25-29 on the sewer-capacity reserve, passed first reading February 17 and second and final reading March 2, both 8-0. On March 2 staff also presented a tiered flow-monitoring plan for moratorium compliance.
The board heard individual requests for reserve capacity one at a time. On June 1 it approved Resolution 26-162, a sewer allocation for two Spring Hill Town Crossing tenants, 8-1.
Utility staff briefed the board on a proposed Columbia force-main connection, described as a long-term partnership that could last up to 40 years, aimed at long-term sewer capacity.
The board adopted Resolution 26-221, the city's Additional Design Requirements for Decentralized Wastewater Systems, on its consent agenda, 7-0.
Ordinance 26-17, a 460-gallon-per-day reserve allocation for a Main Street restaurant expansion, was on the agenda for first reading, with second reading set for October 5. The staff memo says 99,500 of the 100,000-gallon reserve was still unallocated.
The city says the original order followed 29 self-reported effluent exceedance violations between 2023 and 2025. Its August 2025 notice also says the consent-order moratorium remains until the treatment plant meets specified performance standards for 12 consecutive months.
Nothing that ends the moratorium. We read the city's news posts and the Board of Mayor and Aldermen minutes from February through July 2026. The pattern is steady, case-by-case rationing. The board finalized the reserve amendment (Ordinance 26-01) on March 2, then voted on individual reserve requests from businesses. Allocations went to named tenants, and one June vote split 8-1.
The reserve is tiny by design. A September 21, 2026 staff memo says the board had granted 500 gallons per day from the 100,000-gallon reserve so far, and describes the reserve as meant for qualifying nonresidential tenant improvements in existing buildings. For scale, Ordinance 25-29's vacant-lot group works out to 250 gallons a day per lot (62,500 gallons for 250 lots). If you're hoping to carve a new home site out of that reserve, ask the city directly before you count on it.
The longer-term fixes are in motion but not finished. A sewer rehabilitation project aimed at inflow and infiltration started in June 2026 and is expected to run into early 2027. Staff presented a proposed force-main connection to Columbia on June 15. On July 20 the board adopted design requirements for decentralized wastewater systems, the small private treatment plants some developers want to use instead of the city plant. The city's FY27 budget also projects lower development-fee revenue because of the moratorium, which tells you nobody at City Hall expects it to vanish soon.
Sources: the September 21, 2026 agenda packet (Ordinance 26-17 and staff memo), BOMA minutes for March 2, June 1, June 15, and July 20, 2026, and the city's sewer rehabilitation notice.
Not automatically. Septic needs its own approval. Start by finding out whether the parcel already holds vested or allocated sewer capacity. If it doesn't, ask the city which wastewater options it will accept for your use. Septic then has to earn its own permit: enough suitable soil for the system and a backup area, plus the city's land-use sign-off. Some lots can't do either, and it's far cheaper to learn that before closing.
Ask for written confirmation of sewer availability, vested rights, capacity allocation, flow-meter requirements, development status, and any current amendment that applies.
TDEC administers the SSDS permit. Use its regional contact page, approved soil-consultant list, online application, and active-installer lookup.
Williamson is a TDEC contract county. Use the county program for septic questions while still confirming Spring Hill's separate sewer and development requirements.
A project may proceed with documented vested or allocated city sewer capacity, wait for later capacity, use a city-approved decentralized approach where available, or pursue an individually permitted septic system if the site and land-use rules allow it. Each route runs through a different authority, so a contractor can't swap one for another mid-project.
Septic isn't just a theory here. At the April 20, 2026 board meeting, staff reported that one commercial applicant didn't qualify for a decentralized system and had been advised to pursue septic, with staff recommending approval contingent on the required approvals and a long-term maintenance plan (April 20 minutes).
For a Maury County septic route, start with a soil and site evaluation and the TDEC permit process, then compare the permitted system's installation and ownership cost. Building new? The new-construction septic guide sequences the whole thing. Spring Hill's city limits cross the county line, so never assume the same septic office handles two nearby addresses.
About our sources. Maury Septic uses the sources listed below, including Spring Hill's consent-order notices, adopted framework, and current ordinance index. Follow the links for the underlying rules, fees, and guidance.
This page is reviewed against the city's official notices and ordinance index. If you spot something the city has changed that we have not, use the contact page.
City of Spring Hill
Official city summary of the 2025 TDEC consent order and sewer-connection restrictions.
City of Spring Hill
Current capacity-allocation framework adopted January 5, 2026.
City of Spring Hill
Official access to Ordinance 25-29 and the later Ordinance 26-01 amendment to its sewer-capacity reserve.
Tennessee Department of Environment and Conservation
Who needs a permit, application requirements, review timing, current state fees, and inspection duties.
Tennessee Department of Environment and Conservation
Conventional, repair, and alternative-system applications, plus soil-map requirements.
Tennessee Department of Environment and Conservation
Environmental field-office routing for septic-system questions and applications.
Tennessee Department of Environment and Conservation
What an approved consultant evaluates, current qualification rules, and the state consultant list.
Yes. As of September 2026 the city has not announced an end date. The consent order keeps the moratorium in place until the treatment plant meets its performance standards for 12 consecutive months. Meanwhile Ordinance 25-29 governs who gets the remaining capacity, and the board amended its reserve rules with Ordinance 26-01 in March 2026.
No. It means you can't count on a new city sewer connection. Your parcel might already hold vested or allocated capacity. It might fit a city-approved decentralized system, or it might qualify for a TDEC-permitted septic system. Some lots won't support the project at all. The city and TDEC each decide their piece separately.
New projects without vested sewer rights. Homes and businesses already connected keep their service. Ordinance 25-29 then sorted the remaining capacity into groups: existing development agreements, permit-ready vacant lots, critical infrastructure, and a reserve. Rights attach to specific projects, so get the city's answer for your parcel in writing. Nearby construction proves nothing.
TDEC does, through its Columbia Environmental Field Office. Spring Hill also reaches into Williamson County, which runs its own septic program under contract with the state. So check which county your parcel sits in first. The city's land-use approval is a separate step either way.
It's working on it, with no promised date. A 2026 sewer rehabilitation project to cut inflow and infiltration runs into early 2027. In June 2026 staff briefed the board on a proposed force-main connection to Columbia, and in July the board adopted design rules for decentralized wastewater systems. None of that reopens connections by itself.
Related: Spring Hill service area · Maury County permit guide · septic system cost · installation process
Keep your permit, system sketch, and service records together. They help the next professional understand your property.